General construction

Landeskrankenhaus Feldkirch, OP-Spange Süd

Client:
Vlbg. Krankenhausbetriebs GesellschaftmbH
Contract value:
7,36 Mio EUR (in ARGE)
Construction period:
02/2015 - 11/2018

BTV Conversion Bludenz

Client:
Bank für Tirol und Vorarlberg AG
Contract value:
0,31 Mio EUR
Construction period:
11/2014 - 09/2015

Tschagguns school sports centre – Renovation and adaptation

Client:
Land Vorarlberg
Contract value:
0,41 Mio EUR
Construction period:
09/2014 - 09/2015

Propstei St. Gerold - Renovation and extension

Client:
Kloster Einsiedeln / Propstei St. Gerold
Contract value:
-
Construction period:
07/2014 - 12/2014

Kronenwiese residential complex, Schruns

Client:
Revital Bauträger GmbH
Contract value:
1,11 Mio EUR
Construction period:
04/2014 - 09/2014

Montforthaus, Feldkirch

Client:
Agency of Feldkirch
Contract value:
9,90 Mio EUR (in ARGE)
Construction period:
11/2012 - 11/2013

Town house St. Gallenkirch - rebuild

Client:
Gemeinde St. Gallenkirch
Contract value:
0,11 Mio EUR
Construction period:
05/2014 - 08/2014

Fosterhome Birkenwiese, Dornbirn

Client:
Agency of Dornbirn
Contract value:
4,40 Mio EUR
Construction period:
02/2012 - 04/2013

Kindergarten Muntlix

Client:
Community Zwischenwasser
Contract value:
0,36 Mio EUR
Construction period:
10/2012 - 12/2012

Butchery Pfleghar, Bludenz

Client:
Ferdinand Pfleghar
Contract value:
0,30 Mio EUR
Construction period:
02/2012 - 10/2012

Rehabilition and expansion of the Oberau school center, Feldkirch

Client:
Town of Feldkirch
Contract value:
3,37 Mio EUR
Construction period:
06/2010 - 02/2012

Vorarlberg state museum, Bregenz

Client:
Agency of the Vorarlberg state government
Contract value:
5,58 Mio EUR
Construction period:
10/2010 - 11/2011

Villa W, Vienna

Client:
-
Contract value:
-
Construction period:
06/2010 - 07/2011

State hospital, Hohenems

Client:
Voralberger Krankenhaus-Betriebsgesellschaft mbH
Contract value:
0,54 Mio EUR
Construction period:
05/2010 - 08/2010
Erweiterungsbau Gemeindehaus und Neubau Feuerwehrhaus Röns

Town house and fire station, Röns

Client:
Röns municipality
Contract value:
0,96 Mio EUR
Construction period:
05/2009 - 11/2009

Labour market service, Feldkirch

Client:
BIG Bundesimmobiliengesellschaft m.b.H
Contract value:
1,73 Mio EUR
Construction period:
03/2009 - 12/2009

Vorarlberg Arbeiterkammer

Client:
Kammer für Arbeiter und Angestellte für Vorarlberg
Contract value:
2,23 Mio EUR
Construction period:
09/2008 - 11/2008

State hospital, Feldkirch - central kitchen

Client:
Voralberger Krankenhaus-Betriebsgesellschaft mbH
Contract value:
4,71 Mio EUR
Construction period:
09/2008 - 08/2009

WIFI, Dornbirn

Client:
WKV Bildungshaus GmbH
Contract value:
6,45 Mio EUR
Construction period:
11/2005 - 04/2007