Power plant Parbati III
Underground Mining Power station construction
Cavern power plant, pressure shaft, underwater tunnel
Key data
- Country
- India
- Client
- NHPC Ltd.
- Construction method
- conventional tunnelling
- Excavation volume
- 420.000 m³
- Contract value
- 68.4 million EUR (as part of a consortium)
- Construction time
- January 2006 - January 2011
- Excavation diameter / cross-section
- 750 - 900 m²
- Contact
Sekretariat Untertagebau
+43 5 7181-1190
E-Mail