Rodund power stations I and II Latschau basin
Civil Engineering Underground engineering
Key data
- Country
- Austria
- Client
- Vorarlberger Illwerke AG
- Contract value
- 3.92 Mio EUR
- Construction time
- February 2011 - June 2011
- Contact
Sekretariat Tiefbau
+43 5 7181-1690
E-Mail
Under the leadership of JÄGER, the consortium was awarded the contract for all the building work for the reconstruction and rehabilitation of Latschau basin II. The performance ranged from short bore tunnelling in the protection of a pipe shield and large-scale renovations of the existing power plant descent through to the construction of a completely new outlet structure for the future connection between the Latschau and Rifa reservoirs. In total, over 5,000 m³ of concrete was used in a very short time.